Activity Duration Dependency Start 0 9 Start B 5 C 6 B H D 7 C E 9 D F F 4 C G 6 Start H 8 Q37022703

ActivityDurationDependencyStart0A9StartB5AC6B ,HD7CE9D, FF4C, IG6StartH8GI10HJ5I, CK1JL4J, KFinish0E, L

1. Draw the network diagram, including all calculations of nodesusing the following format: 2. List the network paths below: 3.Determine the critical path(s). What is it and what is itsduration? 4. What would happen to the critical path if C took 6days longer than expected? What about if activity L took 6 dayslonger than expected?


Solution


Leave a Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.