Consider the following table of processes and service times: P1 P2 P3P4 P5 Process Service Time 50 150 100 20 5 What would be the completion time for P3 if the operating system uses a First-Come, First- Serve CPU scheduling approach Note: Assume O as the initial starting time 150 50 8030) 200 Show transcribed image text Consider the following table of processes and service times: