Move Furniture 34 Days Plan Move Hire Staff Finalize Movein End 2 Daysmove Equipment 4 2 D Q37176452

Move furniture 34 days Plan move Hire staff Finalize Movein End 2 daysMove equipment 4 2 days 70 days 23 days 6 3 days 0 0 Mo

Move furniture 34 days Plan move Hire staff Finalize Movein End 2 daysMove equipment 4 2 days 70 days 23 days 6 3 days 0 0 Move records 5 1 day Given the above PERT/CPM chart, how many days does it take for the project to end? Select one: 0 a, 13 days O b. 12 days О с. 15 days d. 9 days Show transcribed image text Move furniture