Show all of your steps when working through the followingscheduling algorithms. A. Use the following data to draw a Ganttchart for FCFS scheduling. Show the wait time for each job and theaverage wait time. Process Burst time P1 25 P2 5 P3 10 P4 15 B. Usethe following data to draw a Gantt chart for FCFS scheduling. Showthe wait time for each job and the average wait time. Process Bursttime P1 5 P2 10 P3 15 P4 25 C. What might you infer from thedifference in the average wait times for the two previous questionsand data sets? In other words,